Hi everyone,
I've encountered an issue where some Vulnerability Remediation (VUL) tasks or remediation tasks remain open, despite their associated Vulnerable Items (VITs) being 100% closed. Can anyone help me understand why this discrepancy occurs, and what might be causing it for specific remediation tasks?"

1 ACCEPTED SOLUTION

There will be script include where they configured this logic - state is closed & substate is fixed then close all the related remediation groups or VULs, if not skip the group state updation.

 

Mark as Helpful if you think the answer is helpful 

 

 

Thanks

Yamsani Bhavani

View solution in original post

4 REPLIES 4

Rachna S
Tera Guru

Hi,

 

Did you manage to find the reason for this ?

Hi,

The OOB configuration only closing VULs when it is closed with fixed as substate. If needed add the condition to close the VULs also irrespective of substate.

There will be script include where they configured this logic - state is closed & substate is fixed then close all the related remediation groups or VULs, if not skip the group state updation.

 

Mark as Helpful if you think the answer is helpful 

 

 

Thanks

Yamsani Bhavani