How can we add a planned duration of 0.5 days in the project template?

Ria
Tera Contributor
Currently, when we set the planned duration to 0.5 days, it appears as 0 seconds in the planning console.
3 REPLIES 3

pr8172510
Tera Guru

Hey @Ria,
 The planning console doesn't support fractional days well. Enter 4 hours instead of 0.5 days.

☝️this!

 

Eventually try the decimal "," (comma) instead of "." (dot)

_____
Answers generated by GlideFather. Check for accuracy.

Tanushree Maiti
Tera Patron

Hi @Ria 

 

Refer this KB: KB0552065 Project Scheduling Engine 

ServiceNow calculates durations using standard 8-hour working days. Planning Duration does not accept decimal . So instead of 0.5, input exact hour. 

 

If you still need 0.5 , you have to customize the space with new field addition and map that wherever required.

 

Please Accept the solution if it assisted you with your question & Mark this response as Helpful.
Regards
Tanushree Maiti