How can we add a planned duration of 0.5 days in the project template?
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11m ago
Currently, when we set the planned duration to 0.5 days, it appears as 0 seconds in the planning console.
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
6 seconds ago
Hey @Ria,
The planning console doesn't support fractional days well. Enter 4 hours instead of 0.5 days.