How can we add a planned duration of 0.5 days in the project template?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
Hey @Ria,
The planning console doesn't support fractional days well. Enter 4 hours instead of 0.5 days.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
☝️this!
Eventually try the decimal "," (comma) instead of "." (dot)
Answers generated by GlideFather. Check for accuracy.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
Hi @Ria
Refer this KB: KB0552065 Project Scheduling Engine
ServiceNow calculates durations using standard 8-hour working days. Planning Duration does not accept decimal . So instead of 0.5, input exact hour.
If you still need 0.5 , you have to customize the space with new field addition and map that wherever required.
Regards
Tanushree Maiti
ServiceNow Technical Architect
LinkedIn: https://www.linkedin.com/in/tanushreemaiti