How can we add a planned duration of 0.5 days in the project template?

Ria
Tera Contributor
Currently, when we set the planned duration to 0.5 days, it appears as 0 seconds in the planning console.
1 REPLY 1

pr8172510
Tera Guru

Hey @Ria,
 The planning console doesn't support fractional days well. Enter 4 hours instead of 0.5 days.