Hi everyone , I have a question do you now if in SPM can we check a list of milestones?

2 REPLIES 2

miftikhar20
Kilo Patron

Hi @ANALAURAG,

 

You can check the list of Project Milestone from the Project task table.

  1. Open Project Task[pm_project_task] table.
  2. Set the filter Milestone is True.
    MIftikhar_0-1768854157938.png

 

If my response helped, please mark it as the accepted solution so others can benefit as well.

 

Thanks & Regards,
Muhammad Iftikhar