Marco Nappo_
Mega Guru

This article explain how risk (score_risk field), value (score_value field) and size (score_size field) are calculated in a project, if you are interested on how they are calculated in a demand please refer to this article

Risk, Value and Size are used to calculate the Project Score as described in this article

1. Project Risk Score:

10 if Risk is Critical
6 if Risk is High
4 if  Risk is Low
2 if Risk is Planning

2. Project Size Score:

2 if Cost > 1.000.000
4 if 750K< Cost <1.000.000
5 if 500K< Cost <750K
6 if 250K< Cost <500K
10 if 0 < Cost <250K

3. Project Value Score:

10 if ROI % > 100%
9 if 75< ROI % <100%
8 if  50< ROI % <75%
6 if  25< ROI % <50%
4 if  10< ROI % <25%
2 if 5 < ROI % <10%

Scores are calculated by the Business rules: EntityScorer.updateMetricScore(current);
In particular they are calculated in ScoreCalculator Script Include functions (Risk is calculated in calculateRisk, Value  is calculated in calculateValue, Size is calculated in calculateSize

find_real_file.png

find_real_file.png

 

 

Comments
Bob41
Tera Contributor

Hi, 

I have added two 'High' level 'Risks' to my project, but the 'Risk score' is not updated and showing as zero only. Any idea? Any help is appreciated!

Dhiren Aghera
Tera Guru

This is helpful. So as these fields are editable, based on the above mapping you have shared we have to update these fields? Is my understanding correct?

Also, I see the score files is editable. What is the impact as I don't see any change if I update the score field manually?

find_real_file.png

diegobermudez
Tera Expert

Hi,

 

I´m in the same doubt. Is the project risk calculated form the risk asociated??? The risk field is hidden in project form and doesn´t seem to be affected by the risk asociated so, how is managed the risk in project when it is not originated from demand. Did you find the relationship??

Thanks and Regards!!

Version history
Last update:
‎11-26-2018 04:23 AM
Updated by: