Hello all,
We recently had ITBM implemented and I am running across the an issue where leadership wants to change the available hours of a analyst from 40 hours to 30 in the allocation workbench. I have read through the docs and found that this is set by the default resource management schedule. This schedules hours have been adjusted to 6 hours and the fte hours per day have also been updated in the Properties - Resource module. However, the workbench is still showing 40 hours. Has anyone experienced this same issue? We are currently on London Patch 4 and I have also ensured that I changed the users default schedule to the resource management schedule and still no dice. Any help in the right direction would be appreciated. The photo below is where I am experiencing this.
Solved! Go to Solution.
- Labels:
-
Resource Management
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-05-2019 08:58 AM
After changing the schedule, did you run update capacity UI action for the users?
Check the docs here.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-05-2019 08:58 AM
After changing the schedule, did you run update capacity UI action for the users?
Check the docs here.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-05-2019 10:41 AM
This is exactly what I was looking for thank you!