Project State not changing to "Closing"

Gaurav Garg5
Kilo Contributor

Hello Experts,

I am working on Kingston version of ServiceNow. I am trying to change the phase of an "Executing" project to "Closing". It throws an error: 

 

"Phase can-not be moved to closing state because some subtask is opened". 

 

Looking at this error, I changed the state of last task to Closed Completed". As soon as I did this, project state changed to "Closed Completed" automatically. My need is to keep my project in "Closing" phase and "Work in Progress" state so that I can perform some administrative tasks before completely closing it.

Q: How can I achieve the following:

Project Phase: Closing

Project State: Work in Progress

Project Task State (just last): Work in Progress

1 ACCEPTED SOLUTION

Please change project state to "closed incomplete" which allows you to keep tasks open for that project.

After all tasks are closed, you can change project state to "closed complete".

Please see below documentation.

https://docs.servicenow.com/bundle/kingston-it-business-management/page/product/project-management/task/t_CloseAProject.html?cshalt=yes

Regards,

Sachin

View solution in original post

3 REPLIES 3

Ct111
Giga Sage

I found this useful comment while looking into the below thread hope it might give you direction

 

  • When the last Project Task closes, the Project state automatically changes to Closed. This happens under both Manual and Automatic calculation types. There are several Community threads on how to stop this behavior (here is one). A recommended business process is to have a Task at the end of every Project that would be assigned to the project manager - like 'Validate Project for Closure" and then make it a successor from the last Task, usually a milestone. When the project_manager validates and closes that Task, then the Project would auto-close and you would record the project manager's validation work in a Task.

 

FOr more details read the below link

https://community.servicenow.com/community?id=community_article&sys_id=72aca625dbd0dbc01dcaf3231f96194e

 

Mark my ANSWER as CORRECT and HELPFUL if it gave u idea

Thanks for your response. Just a quick question:

Can I change the phase of project to "Closing" even when one of my project task is in "Work in Progress" state? Is it a best practice doing so?

Please change project state to "closed incomplete" which allows you to keep tasks open for that project.

After all tasks are closed, you can change project state to "closed complete".

Please see below documentation.

https://docs.servicenow.com/bundle/kingston-it-business-management/page/product/project-management/task/t_CloseAProject.html?cshalt=yes