Can you edit a "Processed" Expense Line?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-20-2022 08:07 AM
I have an issue where once an Expense Line has been changed to the "Processed" state, my Project Managers are no longer able to make any updates to the values (read-only). We require the ability to edit these in the event of a change in data or a keying error. Does anyone know what setting or role can be updated to allow Expense Lines to be editable after they reach the "Processed" state?
Thank you in advance.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-22-2022 09:24 AM
This is a slippery slope, Tim. You might want to figure out why they are wrong and go after that instead.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-24-2022 12:34 AM
Same opinion of Renita. Anyway if you decide to rollback the state (modifying acl or with a custom ui action which forces the state), check very well the real rollback of actual, in particular from costplan breakdown, if it's an exp line related to a costplan

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-25-2022 01:38 AM
Hi Tim,
Would not recommend to modify OOTB scripts or rules. Rather to nullify the incurred incorrect expenses, please create one more expense line with the same -ve amount. Also a best practise is to ensure before processing the xpense line to re-check its correctness.