How to update the Cost Type automatically created in Cost Plan from Resource Plan

Tim138
Tera Contributor

When I create a Resource Plan, the corresponding Cost Plan that is created is automatically assigned a Cost Type of "Labor Capex".  Does anyone know where I would go to change this default?  I want it to default to another one of the Cost Type options.

Thank you.

9 REPLIES 9

Sulabh Garg
Mega Sage
Mega Sage

Hi TIm,

Whenever a resource plan is created at demand or project level, the system will automatically create its corresponding cost plans with cost-type as "Labor Capex"image

 

For more information, Please refer this article Relation between resource plan and cost plan

 

Please Mark Correct/helpful, if applicable, Thanks!! 
Regards
Sulabh Garg

Please Mark Correct/helpful, if applicable, Thanks!!
Regards
Sulabh Garg

Hello Sulabh,

My question is how do I change that default.

Please see the below Business rule which Rajesh also mentioned..

BR name - createFromResourcePlan

Script include - Costplan

Screenshot below

find_real_file.png

 

find_real_file.png

 

Please Mark Correct/helpful, if applicable, Thanks!! 
Regards
Sulabh Garg

Please Mark Correct/helpful, if applicable, Thanks!!
Regards
Sulabh Garg

Rajesh_Singh
Kilo Sage
Kilo Sage

Check Create Cost Plan business rule on resource table and see if you can find something.

If you found my response helpful or applicable, please consider marking it as correct or helpful to assist others who may be seeking the same information.

---------------
Regards,
Rajesh Singh