How to update the Cost Type automatically created in Cost Plan from Resource Plan
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-19-2022 10:28 AM
When I create a Resource Plan, the corresponding Cost Plan that is created is automatically assigned a Cost Type of "Labor Capex". Does anyone know where I would go to change this default? I want it to default to another one of the Cost Type options.
Thank you.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-19-2022 12:12 PM
Hi TIm,
Whenever a resource plan is created at demand or project level, the system will automatically create its corresponding cost plans with cost-type as "Labor Capex"
For more information, Please refer this article Relation between resource plan and cost plan
Please Mark ✅ Correct/helpful, if applicable, Thanks!!
Regards
Sulabh Garg
Regards
Sulabh Garg
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-20-2022 08:09 AM
Hello Sulabh,
My question is how do I change that default.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-21-2022 10:35 PM
Please see the below Business rule which Rajesh also mentioned..
BR name - createFromResourcePlan
Script include - Costplan
Screenshot below
Please Mark ✅ Correct/helpful, if applicable, Thanks!!
Regards
Sulabh Garg
Regards
Sulabh Garg

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-19-2022 08:39 PM
Check Create Cost Plan business rule on resource table and see if you can find something.
---------------
Regards,
Rajesh Singh