Changing Project Task Planned End Date not Changing Parent Planned End Date

gfancher
Tera Expert

Occasionally when a Project Manger changes the Planned End Date on a child Project Task the parent is not being updated to that date, even though it is the latest date of all the child tasks. I'm wondering if there is a scenario where this is the intended behavior.

9 REPLIES 9

Miguel Donayre
ServiceNow Employee
ServiceNow Employee

Are you properties set up correctly? 

Miguel Donayre
ServiceNow Employee
ServiceNow Employee

Does this happen to just the planned end date?

sachin_namjoshi
Kilo Patron
Kilo Patron

Below blog should be helpful to you which talks about date calculations for project

 

https://community.servicenow.com/community?id=community_blog&sys_id=87fc66a5dbd0dbc01dcaf3231f9619f9

 

Project Scheduling Engine

 

Project Scheduling Engine - Geneva

 

Regards,

Sachin

gfancher
Tera Expert

Thank you Miguel - "Rollup project start date from tasks" is checked yes in our instance.