Date Entry for tasks - Planned dates and Actual dates

Rita Chang
Kilo Contributor

I'm trying to update planned start and end dates in SPM and have run into a two issues:

  1. When I enter an Actual Start Date, the Planned End Date updates to the same date.  This is the case even if the Planned Start Date is after the Planned End Date.
  2. Sometimes, when I try to update the Planned Start Date with 'Start No Earlier Than' as the constraint, the Planned Start Date reverts back to the original value and no warning or error message appears.

Anyone have ideas on how to handle these situations?

 

1 REPLY 1

Tanushree Maiti
Giga Patron

Hi @Rita Chang 

 

Check this KB: KB0746895 Actual Start/End date behavior changes in Project Management post-London 

 

 

Please mark this response as Helpful & Accept it as solution if it assisted you with your question.
Regards
Tanushree Maiti
ServiceNow Technical Architect
Linkedin: