Hello,
OOB in projects, you can create financial baselines.
The OOB informations are great, still we want to add new informations to the baselines, is it possible ?
The informations that we want are mainly snapshot of resource plans as they were
BR,
Solved! Go to Solution.
- Labels:
-
Project Portfolio Management
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-05-2022 01:50 AM
Hello,
I found a way to do it, what is captured on the baselines is configurable on the baseline API, you can capture data as well as whole tables.
You can configure that by going to "baseline_config" table.
BR,
Hamza.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-02-2022 12:26 PM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-02-2022 12:50 PM
Hello,
The baseline in itself is a snaphot, i will clarify more my requirements :
1 - on the project table we added some new custome fields, i want them to be captured on the baseline.
2 - Regarding resource plans i want them also to be included on the snapshot the same way the costplans are captured in the baseline :
I want to have the list of resource plans captured here.
BR,
Hamza.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-02-2022 01:33 PM
Hi hamza,
This is link to configuration of fields captured in baseline this should solve your first requirement.Try configuring you custom fields here
http://<Instance Name>.servicenow.com/baseline_config.do?sys_id=e273c7270bd203008d9ac74363673aee&sysparm_record_target=baseline_config&sysparm_record_row=1&sysparm_record_rows=4&sysparm_record_list=nameSTARTSWITHproject%5EORDERBYname
2 - Regarding resource plans i want them also to be included on the snapshot the same way the costplans are captured in the baseline :
I cant think of possible way to achieve this OOB.
Thanks!
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-05-2022 01:50 AM
Hello,
I found a way to do it, what is captured on the baselines is configurable on the baseline API, you can capture data as well as whole tables.
You can configure that by going to "baseline_config" table.
BR,
Hamza.