Hi,
I am trying out the external dependency functionality in the planning console and have an issue. I added an external dependency (Hard) to a project task and when I first added it, the dependant task started the day after the other task completed. When I updated the planned end date of the external dependency task in its plan , the dependant task did not take update. I have tried refreshing but it still hasn't updated. What am I doing wrong?