Hi There,
is there any way we can hide Add Task button on project workspace. I tried to hide it but its not present in declarative action/ui action or anywhere else.
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
yesterday
Please open the SN Task Planner 1 config pane. and In Can create project task field click on the
In Can create project task field select the Use static Input option.
Uncheck the option and save the page
Thanks & Regards,
Muhammad Iftikhar
If my response helped, please mark it as the accepted solution so others can benefit as well.
Muhammad Iftikhar
If my response helped, please mark it as the accepted solution so others can benefit as well.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
yesterday
please share screenshots
If my response helped please mark it correct and close the thread so that it benefits future readers.
Ankur
✨ Certified Technical Architect || ✨ 9x ServiceNow MVP || ✨ ServiceNow Community Leader
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
yesterday
Could you explain your use case in more detail, why do you want to hide Add Task button on project workspace (Planning tab)?
This is the basic functionality of planning to add new tasks to project.
Thanks
Anand
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
yesterday
My requirement is to hide Add Task button for project manager/users.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
yesterday
Hi @nowitsvashu ,
This will disable task creation functionality from whole planning tab, you cannot see option Add task below or Add child task from task context menu.
Follow below steps:
Steps to disable the "Can create project task" option in UI Builder:
- Go to UI Builder → Project Workspace → Planning tab.
- In the Body section, select SN Task Planner 1.
- Click on Configure.
- Scroll down to find the Can create project task option.
- Click the pencil icon next to it — it will turn into a checkbox.
- Uncheck the box.
- Click Save to apply the changes.
If this solves your query mark this as correct/helpful.
Thanks
Anand