How do I stop a time card against a closed project?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
09-19-2022 06:12 AM
Is there any way to stop a timecard from being submitted against a closed project?

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
09-19-2022 02:56 PM
Update the filter criteria for time_card.task field to allow Tasks where Parent Project is active.
Hope this helps.
Best Regards,
R

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-03-2022 05:07 AM
Hi,
There seems to be quite a lot of requests of all types to limit resources from creating timecards. I would not limit it in any circumstance. Timecards should be the actual and if actuals are being done on closed projects I would want to know why and not ask the resource to lie (put time on something else).
I challenge this request all the time.