I am new to the SPM Project Planning module. I want to do the following two things but could not find any documentation or figure out how to do this in the UI on my own.
1. Collapse or expand all WBS rows
Is there a way to automatically collapse or example all rows without having to click on each of them individually?
Solved! Go to Solution.
- Labels:
-
Project Portfolio Management
- 580 Views

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-24-2025 06:30 AM
Hi, use the ">" icon in front of Short description column, that should enable all project tasks with sub-tasks of their own to collapse/expand in the Planning page.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-24-2025 06:30 AM
Hi, use the ">" icon in front of Short description column, that should enable all project tasks with sub-tasks of their own to collapse/expand in the Planning page.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-24-2025 06:34 AM
Thank you!! Can't believe I missed that.