How to collapse/expand all WBS tasks

KarrieDash
Tera Expert

I am new to the SPM Project Planning module. I want to do the following two things but could not find any documentation or figure out how to do this in the UI on my own.

 

1. Collapse or expand all WBS rows

Is there a way to automatically collapse or example all rows without having to click on each of them individually?

KarrieDash_0-1740172839929.png

 

1 ACCEPTED SOLUTION

PaulaaO
Mega Sage

Hi, use the ">" icon in front of Short description column, that should enable all project tasks with sub-tasks of their own to collapse/expand in the Planning page.

View solution in original post

2 REPLIES 2

PaulaaO
Mega Sage

Hi, use the ">" icon in front of Short description column, that should enable all project tasks with sub-tasks of their own to collapse/expand in the Planning page.

Thank you!! Can't believe I missed that.