I am trying to create a Resource Assignment directly from the technical view of the sn_plng_att_core_resource_assignment table. I inform some of the data as seen in the first image but when when I click "save", start_date and end_date are deleted and the error message "" is displayed.
What is happening? I cannot find the error, can anybody explain to me what BR or whatever is leading me here?
Thanks for everything!
First image: data is correctly introduced in the form
Second image: start_date and end_date have disappeared and error message is displayed
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
a month ago
Business rule 'Validate start end dates of assignments' will validate the task record has valid start and end times within its record. Does your change record have a planned start and planned end date specified?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
a month ago
Business rule 'Validate start end dates of assignments' will validate the task record has valid start and end times within its record. Does your change record have a planned start and planned end date specified?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
4 weeks ago
Thanks for your help Kieran, I was trying to create an assignment outside of the interval (start_date,end_date).