Hi there,
I would like a suggestion for the tool to be used for the management of resource holidays.
I have tried to use "My calendar" but since I have to enter 24 out of office hours so that the resource is not available on that day, the resource report does not give true data as the resource is available for 16 hours less than the truth.
Do you have any suggestions?
Solved! Go to Solution.
- Labels:
-
Resource Management

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-18-2022 06:21 AM
Hi
The following article explains how to create and manage holidays. Please read the article.
Resource Capacity in Resource Management
If my answer was able to solve your query please mark it as Helpful & Correct.
Thanks,
Abhinay Kumar Nandagiri.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-18-2022 06:21 AM
Hi
The following article explains how to create and manage holidays. Please read the article.
Resource Capacity in Resource Management
If my answer was able to solve your query please mark it as Helpful & Correct.