Managing Agile sprint overlaps and percentage complete
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-13-2024 05:05 AM
Hi,
I have started to use the Agile sprints in Service Now and am looking to move to 2 releases per month. OOB the rules prevent 2 sprints from overlapping. Is there a reason for this not being allowed if you are releasing twice per month? In this scenario, developers would start work on the 2nd sprint before the 1st sprint has completed. How do others manage releasing twice a month?
Secondly, I notice that the burndown chart is not functioning very well as it expects the stories to be closed before it calculates how many points have been delivered. Yet, in reality stories are closed after a sprint has been deployed, so the burndown chart only shows a flat line until the very end. I noticed that on the sprint itself, there is a percentage complete field which is updated throughout the sprint. Is there any visual representation of this field on the agile board? Would be good to understand how this field works.
Thanks.