Hello,
We have Parent Project P001.
@ Project tasks under it. PRJTASK001 and PRJTASK002
We have created a sub project( PRJ0011) under P001.
We want to move the PRJTASK001 and PRJTASK002 from under P001 to PRJ0011.
I tried to do the copy partial project method on P001, but I get copy of PRJTASK001 and PRJTASK002 on the same level as them.
How do I move them to Sub Project, under same Parents project.
All help Appreciated
Thank you

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-29-2024 04:49 PM
Hi @Shree Nag ,
Copy partial project won't help in this case as you have also figured out.
Only way I can think of is to update the parent for PRJTASK001 and PRJTASK002 as sub project( PRJ0011).