Hi all
Wondering if anyone has an easy way to move existing project tasks to another exiting project?
was think a UI action would be good.
issue i have is i can change the project reference field, but looks like there are other connections to the project that i either cant see or cant update...
any and all help would be appreciated.
thanks
Carl
5 REPLIES 5

Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-08-2021 02:02 PM
Following Carlos's approach for moving tasks from one project to another to move tasks to a different phase, I did the following (Quebec):
- Navigated to the destination phase.
- Clicked the Edit button on the Project Tasks related list.
- In the Collection list box, searched for the source tasks and moved them to the Projects Tasks List slushbucket.
- Clicked the Save button.
- Verified the tasks were in the destination phase and no longer in the source phase.