Part one, I am looking to determine the difference between operating in the Project Workspace vs Portfolio Planning Workspace. If there is a difference, what is the difference? What are the pros and cons of each workspace?
- Labels:
-
Project Portfolio Management

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
06-03-2025 09:24 PM - edited 06-03-2025 09:24 PM
Hello @DeAndreH ,
Thanks for reaching out to the community to seek the response.
Feature / Focus Area | Project Workspace | Portfolio Planning Workspace |
---|---|---|
Primary Audience | Project Managers | Portfolio Managers / Strategic Planners |
Purpose | Manage execution of individual projects | Prioritize, plan, and govern investments across initiatives. |
Scope | Single project level (tasks, milestones, resources, risks, report) | Cross-project/program level (demand, projects, programs, portfolios) |
Core Capabilities | - Task management - Gantt charts - Resource assignment - Risk/issues tracking | - Demand intake - managing the dependency across the investments - capacity planning - Funding allocation |
Work Elements | Task boards, Gantt view, status report tracking | Planning and roadmap investments along with the capacity management and financials. |
Real-Time Updates | Project execution status, resource workload | Roll-up metrics from demand and project execution at the program level or maybe at the portfolio level |
Business Value | Ensures on-time, in-scope project delivery | Ensures right investments are funded over the roadmap |
In summary:
-
Use the Project Workspace when you're executing a project and need to manage tasks, milestones, resources, risks, issues, decisions, change requests and timelines.
-
Use Portfolio Planning Workspace when you're deciding which initiatives to fund or prioritize, especially across multiple programs, portfolios, business units etc. Then track the progress of roadmap items from one centralized place.
NOTE: SPM pro license provides the access to Strategic Planning Workspace (SPW) & then strategies, goals association while prioritizing and planning the investments also plays a crucial role from SPW.
Hope this helps and if it does, please mark as correct answer to help me and the community.
Thank You!
Namita Mishra
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
06-04-2025 05:59 AM
@Namita Mishra This is very helpful information, especially the table with the focus areas between the two.