Are operational resource assignments meant to be assigned per user or can they be assigned at a group level? While testing, we are unable to assign at group level and are only successful if we add a resource.
1 REPLY 1

Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎11-01-2024 09:26 AM
Hi @Maddie Wolf ,
Operational resource assignment can be created at the group level as well. Screenshot below.
This will create the resource assignments for all the resources in that group. Screenshot below:
Hope this helps and if it does, please mark the resource as correct to help me and other community members.