I have the following requirements from the business which seem hard to achieve with the way ServiceNow locks down any updates to an existing resource assignment when actual hours are present:
- Adjust those resource allocations within the planned start and end dates as project dates shift
- Regardless of whether actuals have been logged
- Regardless of whether the timeline expands or contracts
- Without needing to manually open and update a large number of individual resource assignments
- Have the allocation spread automatically recalculate based on updated dates
- Regardless if the timeline is contracting or expanding
- Without needing to request additional total time from a resource
- Example: if a resource has 100 hours assigned and the project timeline shifts, those 100 hours should be redistributed across the updated dates
Does anyone have an idea how to achieve this?
2 REPLIES 2
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
an hour ago
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
56m ago
sorry to say I have checked all of those and they wont work. I need to create a new ui action with new functionality.