Hi Team,
I need some assistance. We are updating the com.snc.project.fire_brs_from_planning_console system property to true, which should enable Business Rules to fire on save from the Planning Console. This applies only when inserting or deleting tasks and relations.
When I add a task to the project from the project workspace, I don't see any Business Rules triggered in the system log.
For reference, I haven't written any custom Business Rules; I'm checking the out-of-the-box functionality.
Could someone let me know if any additional configuration is required to trigger Business Rules?
Regards,
Shaik Khajavali.