Resource (Allocated vs. Actual) chart is empty on Project Status Report

bterrance42
Tera Contributor

Project appear to have allocated and actua hours associated with resource plans. The  Resource (Allocated vs. Actual) chart shows No data to display. Where does data for this chart come from? Thanks.

 

1 ACCEPTED SOLUTION

Brandon - have you generated Fiscal calendar in your system?


Reports in project status portal are plotted against fiscal period.



In this case of Resource (actual vs allocated report), x-Axis is going to be Fiscal periods in which the resource plans are going to fall.


View solution in original post

8 REPLIES 8

Thank you Brandon. What version are you on? Do you have the it_portfolio_manager role? Are you using the OOTB Portfolio field without customizations? You went through the 4 steps of budgeting in the Portfolio Workbench for the portfolio, correct?


Brandon - have you generated Fiscal calendar in your system?


Reports in project status portal are plotted against fiscal period.



In this case of Resource (actual vs allocated report), x-Axis is going to be Fiscal periods in which the resource plans are going to fall.


Generating fiscal calendar resolved this issue. Thanks Arun!


shivanipatel
ServiceNow Employee
ServiceNow Employee

Brandon,



We are glad you took advantage of the ServiceNow Community to learn more and to get your questions answered. The Customer Experience Team is working hard to ensure that the Community experience is most optimal for our customers.



If you were not able to receive the answer you hoped for but you do believe that you received clarity in terms of how to proceed, we would greatly appreciate if you could mark the appropriate thread as "Correct Answer". This improves the ServiceNow Community experience.



If you are viewing this from the Community inbox you will not see the correct answer button.   If so, please review How to Mark Answers Correct From Inbox View.



Thanks!


Unknown-1.png