Resource Assignment and rate calculation

MS25
Mega Sage

There are 4 places where we can record rates for resources: 

1. Rate model and Rate lines 

2. Rate on Resource Role 

3. Rate of Resource Group 

4. Default Rate system property

 

 

On top of that we have a rate over ride (which is simply over rise a rate when creating resource assignment) 

 

My confusion is around Resource assignment only (not resource plan please) - we are using a new format of resource assignment as new implementation.

 

Which takes precedence if rate is defined for all 4 options? What will be the order? 

 

1 ACCEPTED SOLUTION

miftikhar20
Kilo Patron

Hello @MS25,

Based on my experience and ServiceNow guidance, the rate precedence for Resource Assignments works like this:

  1. Rate Override on the Resource Assignment: if you manually enter a rate here, it always takes top priority.

  2. Rate Model assigned to the project or demand: if no override exists, the system uses the rate defined in the Rate Model (this can consider the resource’s role, group, or other criteria).

  3. If no Rate Model is available:

    • Group or Role rates are applied based on the resource plan type.

    4. Default Rate system property: if none of the above are defined, the system falls back to the default rate.

Related Community discussions:
What is the difference between 1) RESOURCE ROLE rate vs 2) RATE MODEL - role rate?

Rate Model - User Rate - Group Rate - Role Rate? Which One first?

If my response helped, please mark it as the accepted solution so others can benefit as well.

Thanks & Regards,
Muhammad Iftikhar

If my response helped, please mark it as the accepted solution so others can benefit as well.

View solution in original post

4 REPLIES 4

miftikhar20
Kilo Patron

Hello @MS25,

Based on my experience and ServiceNow guidance, the rate precedence for Resource Assignments works like this:

  1. Rate Override on the Resource Assignment: if you manually enter a rate here, it always takes top priority.

  2. Rate Model assigned to the project or demand: if no override exists, the system uses the rate defined in the Rate Model (this can consider the resource’s role, group, or other criteria).

  3. If no Rate Model is available:

    • Group or Role rates are applied based on the resource plan type.

    4. Default Rate system property: if none of the above are defined, the system falls back to the default rate.

Related Community discussions:
What is the difference between 1) RESOURCE ROLE rate vs 2) RATE MODEL - role rate?

Rate Model - User Rate - Group Rate - Role Rate? Which One first?

If my response helped, please mark it as the accepted solution so others can benefit as well.

Thanks & Regards,
Muhammad Iftikhar

If my response helped, please mark it as the accepted solution so others can benefit as well.

should we configure any assosiation with rate model for resource assignment 

Hi @JayanthiHCL ,

You do not need to configure any association with rate model for resource assignment. To fetch the rates from rate model to your project, please refer the point 2 in @miftikhar20 's response.

 

Thank You!

Namita Mishra

Thank you @Namita Mishra Appreciate your swift response.

When rate lines are changed , the recalculate resource costs in the RA does not recalculate the related resource plan or cost plan.
So what: If we ever move to quarterly or bi annual rate updates (or RAs that cross from year to year) we will have incorrect cost roll ups.

@miftikhar20