Resource Assignment and rate calculation
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 hours ago
There are 4 places where we can record rates for resources:
1. Rate model and Rate lines
2. Rate on Resource Role
3. Rate of Resource Group
4. Default Rate system property
On top of that we have a rate over ride (which is simply over rise a rate when creating resource assignment)
My confusion is around Resource assignment only (not resource plan please) - we are using a new format of resource assignment as new implementation.
Which takes precedence if rate is defined for all 4 options? What will be the order?
0 REPLIES 0