10-11-2022 10:34 AM
Hi Team,
I am trying to allocate resource from allocation workbench for a role type resource plan. But for all resource's the availability is showing Zero. Those resource's are not allocated to any resource plan. All are new user's.
How to verify why it's showing availability is zero. Could you help me to understand the process.
Thanks.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-11-2022 10:46 AM
Did you setup capacity for these resources?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-11-2022 11:56 PM
No, For few resource I haven't setup any capacity but for them I am able to see the availabity, For few of the resources it's showing zero.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-28-2024 10:47 PM
Hi @Uma2 ! How did you solve this issue? Do you recall? We face the same and we don't understand how can we know in advance.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-28-2024 11:12 PM
Hi @dianachiriloiu ,
Hopefully you will get a response from @Uma2 .
In case not, feel free to setup zoom call with me..... If the root cause is what I am thinking, then I should be able to help.
Hope this helps!