How are others using resource groups and assigning a group to a resource plan, which is assigned to a task, and managing new resources into the group and updating the resource plan? We can't a good way of maintaining the group to resource plan relationship with new group members.
Labels:
- Labels:
-
Project Portfolio Management
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-29-2024 12:37 PM
I would advise using a new resource plan, not updating the existing one. If you have a new resource on a project that just joined a group, create a user-based resource plan for that new resource.