- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-30-2024 09:13 AM
Can someone help me to perform validation "Resource plan date should be under demand plan start date" while creating resource plan.
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-30-2024 09:19 AM
Hi @MK-p ,
You can achieve this by doing configuration. Set this property to true.
Property Name: com.snc.resource_management.do_not_allow_resource_plan_dates_outside_project_demand_dates
-------------------------------------------------------------------------
If you found my response helpful, please consider selecting "Accept as Solution" and marking it as "Helpful." This not only supports me but also benefits the community.
Regards
Runjay Patel - ServiceNow Solution Architect
YouTube: https://www.youtube.com/@RunjayP
LinkedIn: https://www.linkedin.com/in/runjay
-------------------------------------------------------------------------
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-30-2024 09:19 AM
Hi @MK-p ,
You can achieve this by doing configuration. Set this property to true.
Property Name: com.snc.resource_management.do_not_allow_resource_plan_dates_outside_project_demand_dates
-------------------------------------------------------------------------
If you found my response helpful, please consider selecting "Accept as Solution" and marking it as "Helpful." This not only supports me but also benefits the community.
Regards
Runjay Patel - ServiceNow Solution Architect
YouTube: https://www.youtube.com/@RunjayP
LinkedIn: https://www.linkedin.com/in/runjay
-------------------------------------------------------------------------