Can someone help me to perform validation "Resource plan date should be under demand plan start date" while creating resource plan. 

1 ACCEPTED SOLUTION

Runjay Patel
Giga Sage

Hi @MK-p ,

 

You can achieve this by doing configuration. Set this property to true.

Property Name: com.snc.resource_management.do_not_allow_resource_plan_dates_outside_project_demand_dates


RunjayPatel_1-1735579147183.png

 

 

 

-------------------------------------------------------------------------

If you found my response helpful, please consider selecting "Accept as Solution" and marking it as "Helpful." This not only supports me but also benefits the community.


Regards
Runjay Patel - ServiceNow Solution Architect
YouTube: https://www.youtube.com/@RunjayP
LinkedIn: https://www.linkedin.com/in/runjay

-------------------------------------------------------------------------

 

View solution in original post

1 REPLY 1

Runjay Patel
Giga Sage

Hi @MK-p ,

 

You can achieve this by doing configuration. Set this property to true.

Property Name: com.snc.resource_management.do_not_allow_resource_plan_dates_outside_project_demand_dates


RunjayPatel_1-1735579147183.png

 

 

 

-------------------------------------------------------------------------

If you found my response helpful, please consider selecting "Accept as Solution" and marking it as "Helpful." This not only supports me but also benefits the community.


Regards
Runjay Patel - ServiceNow Solution Architect
YouTube: https://www.youtube.com/@RunjayP