Resource Plan Planned Cost

rad2
Mega Sage

Hello,

I have a scenario where i want to add cost for external labour and also hours for internal labour. The external cost needs to be added to the planned cost(calculated based on hours and internal rate card). How can this be possible in Resource Plan

Thank you

1 REPLY 1

Dhiren Aghera
Tera Guru

Hi @rad2 Have u tried using the rate model where you can define the external and internal labor rates.