RIDAC: Example from practice

stefan_hasbach
Tera Contributor

Hi community,

we are still considering how to use RIDAC in ITBM because today we only use actions and project change requests. Can somebody give an example from practice how to use the ridac workflow as described in snow documentation?

find_real_file.png

Thanks in advance and regards,

Stefan

1 ACCEPTED SOLUTION

Tim Leggett
Kilo Expert

Hi Stefan,

Let's say you have identified a risk that the Resources may not be available to do the work and this has now happened, for example an emergency has happened and limited resources are available.

You would then convert to an issue and close the risk as it has been realised. The issue could be addressed by a mitigation plan you had in place or some other way e.g. you could then create a decision to put the project on hold or hire in additional contract labour to do the work which would involve increased costs and a change request for the project.

Therefore you have created a trail of work that has led to an outcome and all recorded on the project.

Hope that helps.

Tim

View solution in original post

5 REPLIES 5

krishna301
ServiceNow Employee
ServiceNow Employee

Hi Stefan,

 

Though the picture depicts, that the flow is from RISK -> Project Change request, the feature is so flexible that you can start at anypoint and end at anypoint in the forward direction(RIDAC->).

 

If an organization is using only Action and Project Change Requests, they can convert Actions into Project Change Request using this RIDAC feature. 

 

Regards,

Krishna.

Tim Leggett
Kilo Expert

Hi Stefan,

Let's say you have identified a risk that the Resources may not be available to do the work and this has now happened, for example an emergency has happened and limited resources are available.

You would then convert to an issue and close the risk as it has been realised. The issue could be addressed by a mitigation plan you had in place or some other way e.g. you could then create a decision to put the project on hold or hire in additional contract labour to do the work which would involve increased costs and a change request for the project.

Therefore you have created a trail of work that has led to an outcome and all recorded on the project.

Hope that helps.

Tim

Hi Tim, thanks for the use case, appreciate it. Can i check why you don't have an 'Action' in your scenario please?

stefan_hasbach
Tera Contributor

Thank you very much Tim, Krishna!

Regards,

Stefan