I would like to change the calendar view in the planning console.
I want the calendar quarter to start in April instead of January.
5 REPLIES 5
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎06-11-2024 01:51 AM
Hi @RyoyaFukuda, I think I faced a similar use case in my experience with Work4flow. Give the below steps a try:
- Navigate to the "Strategic Planning Workspace" in the SPM module.
- Click on the "Configuration" icon (gear icon) in the top-right corner.
- Select "Configure Strategic Planning" from the dropdown menu.
- In the "Configure Strategic Planning" window, locate the "Calendar Quarter Start Month" field.
- Change the value of this field from "January" to "April."
- Click the "Save" button to apply the changes.
Let me know if it doesn't work. I'll be happy to assist.