Is there an easy way to just enter in and see planned cost and actual cost of work under a portfolio? (i.e., demands, projects, programs, etc.)

4 REPLIES 4

Dhiren Aghera
Tera Guru

@Connie9 Have a look at the PMO Dashboard >> Summary page where you can filter respective portfolio and you see cost details rolled up at the Portfolio level like planned cost, Actual cost, etc...

 

DhirenAghera_0-1697640389874.png

 

yes but how are you able to enter in the 'Actual cost'? I know that the 'Planned cost' is calculated by creating the Cost plans to a project that will roll up to the program or portfolio.

Also they want to see the list of the records as well like columns and rows. I know there's the 'Investment Portal' that can give you that kind of view but still not sure how to be able to enter in actuals.

Dhiren Aghera
Tera Guru

Hi @Connie9 actuals are mostly entered through expense lines against a cost plan (planned cost) and that is what gets rolled up at Project, Program level.