SPM Portfolio Planning - Revert Scenario Approval
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Wednesday
Hi Community,
I created a portfolio plan in SPM -> Portfolio Planning. Then I created a scenario and approved it. As a result in the Financials tab all the budgets got populated accordingly.
However, I want to reuse the portfolio plan that I created for further demonstrations and I want the Target and the Target balance rows clear.
Question: Is there a way to revert this scenario approval?
Best,
Mariya
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Wednesday
Once a scenario is approved in SPM Portfolio Planning, the financial values are typically committed/populated into the portfolio plan and there is no direct “Undo Approval” button available OOTB in many versions.
You can try the following approaches depending on your instance/version:
1. Check if the scenario state can be manually reverted from Approved back to Draft/Planning.
- Some implementations restrict this through business rules/workflows.
2. Review related financial tables/target balance records populated during approval.
- In some cases, clearing the generated target rows manually (or via background script in non-prod) may be required.
3. If this is only for demo purposes, consider:
- duplicating the original portfolio plan before approval
- or restoring from a clean baseline/demo data set
4. Also verify whether a rollback context or transaction was generated during approval:
- System Diagnostics → Transactions
- Rollback & Recovery (if enabled/customized)
5. If approvals were driven through Flow Designer/workflows, there may be custom logic preventing reversal.
I would recommend testing in a sub-prod instance first because reverting approved financial data can impact related budget calculations and downstream planning records.
please mark helpful if this solves your query, Thank you
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Wednesday
Hi @mariyatodor
Revert scenario approval is not supported feature of OOB.
Only while approving a scenario, you can:
- Select Convert In-plan Demands to Projects toggle to convert the prioritized demands to projects automatically and build a functional portfolio plan.
- Delete the remaining scenarios by selecting the Delete other scenarios toggle.
- Enter a reason for approving the scenario in the Notes field.
Refer: Announcing Scenario Planning with Financials in Strategic Planning Workspace