- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
05-25-2026 04:58 AM
I created a project and entered a budget under the Project Budget tab, which is reflected in Project → Details → Budget Cost. However, when I navigate to the Financials tab, the budget value appears as 0.
I have tested this with different roles, including Portfolio Manager, Project Manager, and Admin, but the issue persists. I’ve also reviewed the configuration settings, and everything seems to be correctly enabled.
For reference, I am currently using the Zurich version.
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
06-04-2026 10:21 PM
Hi @pranaybarmo when the 'enable_budget_allocation_v2' property is set to true, you should be allocation budget from financials->Budget allocation display mode for the budget to be populated correctly. The 'Project budget' tab is not available out of the box in the project workspace.
Please review the following link to learn more about the 'budget allocation' display mode - https://www.servicenow.com/community/spm-articles/new-flexible-budget-allocation-capability-in-spm-d...
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
05-28-2026 02:49 AM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
06-04-2026 10:21 PM
Hi @pranaybarmo when the 'enable_budget_allocation_v2' property is set to true, you should be allocation budget from financials->Budget allocation display mode for the budget to be populated correctly. The 'Project budget' tab is not available out of the box in the project workspace.
Please review the following link to learn more about the 'budget allocation' display mode - https://www.servicenow.com/community/spm-articles/new-flexible-budget-allocation-capability-in-spm-d...