Updating & deleting Resource Allocations (in allocated state)

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-27-2017 11:14 AM
I'm trying to determine what the best approach to handle Resource Allocation changes once a project is underway. I perused the Community however cannot find the answer I'm hoping to find.
Example:
You a have Project and Resource Plan with hard allocations. A 100 hours Resource Plan runs from May 1 - August 31. The allocates make for 25 hours per month. It's now July and I have to change the 25 hours to 50 hours because of scope creep (or whatever) for a total of 125 hours. I can't edit the allocation because we're in July.
I need to change the hours to 50 and have the Resource Manager approve the change. I would like to do this in the simplest way. If I change the Resource Plan to 125 hours and save it, it does appear to go back to a requested state, but then it would divide the additional 25 hours among the four months. I do not wish to change any of the other allocations. I simply would like to change the one value in the Resource Allocation and have the request triggered for just that change.
Thanks for your feedback.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-28-2017 05:12 AM
For reasons you've mentioned, if you could modify the existing one, the hours would splits across the months. I'd recommend you take a look at Copy Resource Plan under Related Links. This will copy the existing Allocated Plan into a new Plan in Draft state. That will allow you to quickly change the dates and hours and submit: