Hi, I wonder if I am doing something wrong when allocating resources to a project.  This is what I am doing:

I had users assigned ppm_resource roles, and then imported project from MS Project.

For the tasks that had users assigned in MS Project, resources were assigned. 

However, when I try to manually add users to tasks, I cannot assign them (they are not available in the assignment lookup either).  What could be the issue?

I have run a report to verify the user roles and the users are assigned pps_resource roles.  I have pps_admin, resource/project/portfolio/program_manager roles, so it should not be an issue with privileges too.  

 

Any help would be great as I could not find anything in the documentation or forum regarding this issue.

cheers

Ashu

10 REPLIES 10

mark141230
Tera Expert

Thanks Guys,

 

After I made my research I found out that the resource plan hours is zero thus the system is unable to create allocation so I wont be able to view the user.

 

thanks again guys