I see tables like
- resource_aggregate_monthly
- resource_aggregate_daily
- resource_allocation_daily
What's the use of these? How they get populated? What should I expect if I run reports on these or should I run reports one these if my goal is to see the requested, confirmed, allocated info for the resources?
Please suggest.
Solved! Go to Solution.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-18-2021 08:21 PM
Hi
Refer to this article to get detailed information on resource aggregates.
If my answer was able to solve your query please mark it as Helpful & Correct.
Thanks,
Abhinay Kumar Nandagiri.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-17-2021 08:30 AM
These tables are what ServiceNow uses to allocate the time to the resources and spread it out divided over the timespan.
For instance a resource plan for a group of 3 with 100 hours each for the next 3 months. ServiceNow Will divide the time over Months and further over days - so 33 hours for each person divided over a mth and approx 1 hour a day.
These data points are used later when you look up the Group users allocations in Resource Reports/ Workbench and try to see how much time they have available for other projects in the future.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-18-2021 08:21 PM
Hi
Refer to this article to get detailed information on resource aggregates.
If my answer was able to solve your query please mark it as Helpful & Correct.
Thanks,
Abhinay Kumar Nandagiri.