What Can't Project Planned End Date/Duration Be Changed

Kevin21
Tera Contributor

This is a brand new project record created from a Demand

Planned End Date cannot be altered, when I hover over I see Record has children so this field is calculated from child values

Planned duration also cannot be altered with the same message as above

Project Status is Pending

Project Tasks are empty

find_real_file.png

7 REPLIES 7

kellykaufmann
Mega Guru

Hmmmm out of curiosity, have you created multiple projects from this same Demand?



What version are you on?


Hi Kelly,



A single project was created from the Demand.



Current Version is Fuji (Helsinki in 2 weeks) but of course this can't wait.



Kevin


I would open a Hi ticket so they can dig in.



On Jan 20, 2017 3:07 PM, "kevind16" <community-no-reply@servicenow.com>


Rajendra Muppa1
Tera Contributor

Hi Kevin,



We have same issue in our project, have you got the solution?



If you have any solution please help me on this, Thank you.



Regards,


Raj