This is a brand new project record created from a Demand
Planned End Date cannot be altered, when I hover over I see Record has children so this field is calculated from child values
Planned duration also cannot be altered with the same message as above
Project Status is Pending
Project Tasks are empty
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎01-20-2017 01:02 PM
Hmmmm out of curiosity, have you created multiple projects from this same Demand?
What version are you on?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎01-20-2017 01:07 PM
Hi Kelly,
A single project was created from the Demand.
Current Version is Fuji (Helsinki in 2 weeks) but of course this can't wait.
Kevin
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎01-20-2017 01:48 PM
I would open a Hi ticket so they can dig in.
On Jan 20, 2017 3:07 PM, "kevind16" <community-no-reply@servicenow.com>

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎11-01-2017 02:20 PM
Hi Kevin,
We have same issue in our project, have you got the solution?
If you have any solution please help me on this, Thank you.
Regards,
Raj