07-15-2019 07:08 AM
In the instance that we use, I am trying to switch my progress from the state In Progress to On Hold. The error I am receving is this: "Updating project state from Work In Progress to Pending or Open is not allowed. Update all tasks state to Open to set project state to Open. "
Is there a different way to get around this issue besides having to set all the task to open which resets all to 0 percent.
Thanks
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
07-15-2019 10:06 AM
Please navigate to project task related list on your project and make sure that all project tasks are in open state before changing project state to Pending.
Regards,
Sachin
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
11-03-2023 11:19 AM
So you are saying that if I have a project with 5 tasks and 2 of those tasks are complete but the others are in progress or on hold for whatever reason I cannot switch the project state to pending?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
09-11-2025 08:08 AM
I don't really understand why a project, with partial task already closed (so with an existing progression), cannot be changed to Pending without replacing all the earlier closed task to pending. It 's not a normal way to place a partial executed project to a pending (on-Hold) state. What about the global realization %? If I change all the closed task to pending, my project is back to 0% of realization. That's not a proper way to manage it...
Pending should inform that the project is waiting about something and nothing is work in progress. But the already closed tasks should remain closed!