Why does updating a resource assignment not affect the cost plan?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-23-2026 12:01 AM
If we alter a project resource assignment with a revised effort and recalculate costs we see the expected adjustment. If we change a role to a different one (which has a different rate) and recalculate, we do not see a cost adjustment. If we do both of these things we do see a change to cost and using the updated rate as we would expect.
Why would changing the role alone not apply the new rate and adjust the cost?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-23-2026 06:00 AM
cost are generated based upon the primary attributes, also the defined rate model such as Group, role, user per your org.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-26-2026 01:58 AM
We already have role as a primary attribute and have rates for them.