Monday
We are setting up to migrate from Resource Plan to Resource Assignment. When we are using Resource Plans, the Cost Plan is generated when the Resource Plan is created and approved. For the Resource Assignment, it requires the user to manually click the 'Generate labor cost' button in order to generate the Cost Plans.
What is the recommendation of automizing the cost plan [generate labor cost] creation similar to the Resource Plan works?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Monday - last edited Monday
Hi @Konstantin7
In the new experience, when resource assignments are in use, labor costs must be generated—this behavior is by design.
Refer: Generate labor cost plans by individual resources based on Resource Assignments
A Practical Guide to Resource Assignments
Attribute based labor costs generation for Demands, Projects and Epics - How to setup and use
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Monday - last edited Monday
Hi @Konstantin7 ,
You are correct that in the resource assignments, you have to click on the 'Generate Labor Cost' to generate the labor cost.
As a best practice, you can activate the scheduled job - Generate Labor Costs For Epic and other planning items - to automatically generate labor costs for attribute-based resource assignments.
Hope this helps and if it does please mark this as a correct response to help me and the community.
Happy SPM Journey!
Thank You!
Namita Mishra
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
16 hours ago
What would the negative impact be (if there are any) if we create a business rule that would run when the Resource Assignment is assigned to a user?