Resource Assignment created for a group generates resource assignment for each Employee profile
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
Hello,
we are facing an issue when resource assignment (Assignment type= Group) the resources assignments are generated for each user that has employee profile, ignoring the Primary resource group completely.
Anyone has experience the same issue? Version ot RMW is 5.7.0, PW 7.3.1
Issue is on all instance.
Thank you very much
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
3 weeks ago
Hi , the system is designed to generate an assignment for each user in the group. Is you issue that the system is effectively ignoring the group, and cycling over every possible user? Regardless of group membership?