Hard Depenencies with project ppm task

vs00884087
Tera Contributor

I wanted to know how I can create a Hard Dependency within two project tasks.

Example

PRJ0001- contains 2 tasks prjtask001, prjtask002 and prjtask003.

Now I want a hard dependency  with two scenarios

Scenario-1: prjtask003 cant be closed completed unless and until prjtask002 is 'closed complete'

Scenario-2: prjtask002 should not be progressed(in-progress) until prjtask001 is 'closed complete'

 

Currently I'm able to close the Successor PPM task despite the state of predecessor. I have tried with both 'Start to Finish' and 'Finish to Finish' kind of dependency

 