When I set up cloning in a production environment, how many days in advance do I need to submit it?
Solved! Go to Solution.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎10-18-2024 02:09 AM
@ayano In ServiceNow, the ability to set a clone schedule depends on the lead time required by the system. Typically, you cannot schedule a clone less than 24 hours in advance due to the time needed for planning and resource allocation. However, this timeframe might vary depending on instance size, ServiceNow version etc.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎10-17-2024 09:55 PM
When scheduling a cloning operation in ServiceNow for a production environment, it is generally recommended to submit the request at least 7 to 14 days in advance. The exact timeframe can vary depending on the specific policies and processes of your organization, as well as the complexity of the clone.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎10-18-2024 12:33 AM
Hi @Sandeep Rajput ,
Thank you for your comment.
In my experience, I have been unable to set a schedule for cloning if it is too close to the schedule.
Do you know how many days in advance you can't set a schedule?

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎10-18-2024 02:09 AM
@ayano In ServiceNow, the ability to set a clone schedule depends on the lead time required by the system. Typically, you cannot schedule a clone less than 24 hours in advance due to the time needed for planning and resource allocation. However, this timeframe might vary depending on instance size, ServiceNow version etc.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎10-17-2024 10:07 PM
Hi @ayano
As suggested by @Sandeep Rajput 7- 14 days in advance is good period , also you need time to inform your dev team to take back up of update set as well.
If my response proves useful, please indicate its helpfulness by selecting " Accept as Solution" and " Helpful." This action benefits both the community and me.
Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
Topmate: https://topmate.io/atul_grover_lng [ Connect for 1-1 Session]
****************************************************************************************************************