Hi Lisa,Triage board will be available at the team level,In the dropdown at the top-left, you have selected the context as Portfolio, Please set the context as Team.Cheers.
Hi Darren, The percentage in the UI is based on the field, 'Percent Completed by Estimate', which is the sum of story points of completed stories in the epic divided by the sum of story points of all stories in epic' ,The 'Percent Complete' field, as...