Set the budget of a project according to the fiscal years.
시작하기 전에
Role required: it_portfolio_manager
프로시저
-
Open the project form.
-
In the related links, select Project Budget.
The Project Budget dialog box opens.
-
Select the fiscal year for which you want to set the budget for the
project.
-
Enter the amounts for Capex Budget and Opex
Budget.
The Total Budget is updated with the sum of capex
and opex amounts.
-
Select OK.
- If the project does not have any cost plan associated, then project budget is distributed by honoring planned start and end dates of the project.
- If the project has any cost plan associated, then project budget is distributed by honoring the cost plan fiscal periods.
결과
The project budget for the selected year appears in the Project
Budget related list. You can click the amounts in the list to revise
them.