Create a milestone

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • A milestone is a project task with a duration of zero (0). Use milestones to mark key dates in your project, such as key decision points, approvals, and holidays. Milestones are treated like any other project task and you can create dependencies between tasks and milestones.

    시작하기 전에

    Role required: it_project_manager

    이 태스크 정보

    주:
    Milestones cannot be shared between projects unless one project is nested under another project.

    프로시저

    1. Create a project task and give the Duration field a value of 0.
    2. Open the planning console Gantt chart and verify that it appears as a diamond.
      You can also convert a task to milestone through Planning console tasks.

    결과

    그림 1. Milestone
    Milestone example